07/10/2026
Big progress at Wattle — September construction update.
We filmed on site in late September and walked every level, from level two to the top floor. The timeline hasn't moved.
Practical completion is still tracking January/February 2027, which puts settlement around May/June. It could be earlier. We'll know more as we get closer.
Where Wattle is up to right now:
Level 2 — plasterboard up, kitchen cabinetry going in, walk-in pantries framed, robe joinery underway, bathrooms at rough-in
Level 3 — balcony tiling and balustrades going on, behind the double-glazed sliders
Level 4 — plasterboard complete, finishing joinery staged and ready
Level 5 — steel-stud framing, insulation and services rough-in
Top floor — still at frame stage, external rendering underway outside
Banksia — basement excavation underway next door, excavators working alongside the completed buildings
Wattle is an active construction site, so we can't take anyone through it yet. The video is how you see inside — watch the full walkthrough above.
To see a finished apartment in person, our display apartment in the Magnolia building is open Thursday to Sunday, 10am–3pm, at 221 Bloomfield Street, Cleveland. Book a time at lagunawaters.com.au, or call Cody Fraser on 0403 650 732.