TRL Engineering

TRL Engineering TRL Engineering cater for underground petroleum storage tanks, primarily service station underground

Work commences on Mobil Havelock NorthFIAL Changeover In ProgressTank 1 Completion on Program (+/- 1 day)0 IncidentsAll ...
01/06/2026

Work commences on Mobil Havelock North

FIAL Changeover In Progress
Tank 1 Completion on Program (+/- 1 day)
0 Incidents

All ITP Hold Points Signed
Tank Build Status, Tank Access & Current Stage
Clean Sanding S1 S2 S3 Final Test Tank In Progress
T1 - Tank cleaned. Adequate condition post-clean, no issues or defects to report
T2 - Not Started
T3 (50kL) - Next 7 Days
Activity Notes
T1 - Stage 1
Stage 1 commencing today
T1 - Stage 2
Stage 2 - Expected completion end of the week

All new onboarded personnel are adequately trained in site processes & high risk activities

Progress for Mobil Verrans Corner* Overall progress: 27% complete.* Schedule: On program, tracking within ±1 day of sche...
30/05/2026

Progress for Mobil Verrans Corner

* Overall progress: 27% complete.
* Schedule: On program, tracking within ±1 day of schedule.
* Forecast completion: Remains on target for 17 July 2026.
* Safety: Zero incidents recorded.
* Quality: All ITP hold points have been signed off.

Current Status
* FIAL changeover is currently in progress.
* Tank 3 (30kL ADO): 100% complete.
* Tank 1 (50kL): Not yet started.
* Tank 2 (50kL): Not yet started and is the current focus.

Overall: The project is progressing safely and on schedule, with Tank 3 completed and work on Tank 2 scheduled to begin immediately after the public holiday. No significant risks or quality concerns have been reported.

Mobil Waipukurau – Project Summary Overall project completion is at 77% and remains on program (+/- 1 day).Safety perfor...
10/05/2026

Mobil Waipukurau – Project Summary

Overall project completion is at 77% and remains on program (+/- 1 day).
Safety performance remains strong with 0 incidents recorded.
#
Quality requirements are being met, with all ITP hold points signed off.
* Tank 1 (50kL) and Tank 2 (50kL) are now 100% complete.
* Tank 3 (30kL) has not yet started (0%).
The TRL team has completed work on Tanks 1 and 2 and will return to site during the TTU stage to complete Tank 3.

Planned and forecast finish dates are currently pending remobilisation back to site.
There are no major project risks identified at this stage.
No active workfront or immediate milestone activities are currently listed.

The TRL Engineering team have completed all works at Mobil Mt Richmond. All four tanks have been successfully upgraded, ...
25/04/2026

The TRL Engineering team have completed all works at Mobil Mt Richmond.

All four tanks have been successfully upgraded, with the final tank passing integrity testing this morning. TRL will complete site demobilisation

It’s also worth noting that TRL will be back on site during the TTU to install the turret collars which facilitate the Fibrelite installation

Full project documentation will be compiled and submitted to all relevant parties.

Once again, thanks to Chris and the Fuel Installations team for all the assistance throughout this project.

Mobil Mt Richmond – Weekly ReportOverall Progress* 92% complete* Project is on schedule * Planned finish: 22-Apr-26* For...
17/04/2026

Mobil Mt Richmond – Weekly Report

Overall Progress
* 92% complete
* Project is on schedule
* Planned finish: 22-Apr-26
* Forecast finish: 24-Apr-26

Current Work
Focus is on Tank 4 (T4):
Stage 3 completed
Tissue layers & striker plate installed
Blue solution installation & leak testing completed (by 21/04)
Other tanks (T1, T2, T3) are 100% complete

Next Steps (Next 7 Days)
T4 scanning & integrity testing scheduled for 24/04
Team expects to pack up by end of week
Awaiting confirmation for shipping container removal

Safety & Quality
0 incidents
All ITP hold points signed off
Team completed working at heights refresher training

Bottom Line
The project is nearly complete, on track, and low risk, with final testing on Tank 4 being the last key milestone before wrap-up.

Mobil Waipukurau Overall Progress* 43% complete* Project is on schedule (1 day ahead)* No safety incidents* Quality on t...
17/04/2026

Mobil Waipukurau Overall Progress

* 43% complete
* Project is on schedule (1 day ahead)
* No safety incidents
* Quality on track – all ITP hold points signed

Current Work
Active workfront: Tank 2 – Stage 1 & Stage 2
Tank 2 – Stage 2 expected completion: 24 April

Tank Status
T1 (50kL): 98% → Complete
T2 (50kL): 91% → 32% through current stage
T3 (30kL): Not started

Upcoming
Continue work Tank 2 Stage 2
Anzac Day long weekend: Team off, returning Tuesday 28 April

Project OverviewProject: Mobil Mt RichmondWeek Ending: 10 Apr 2026Planned Finish: 22 Apr 2026Forecast Finish: 24 Apr 202...
12/04/2026

Project Overview
Project: Mobil Mt Richmond
Week Ending: 10 Apr 2026
Planned Finish: 22 Apr 2026
Forecast Finish: 24 Apr 2026
Current Status
Overall Completion: 84%
Active Workfront: Tank 4 – Stage 1
Next Milestone: Tank 4 – Stage 2
Schedule: On program
Safety: 0 incidents
Quality: All ITP hold points signed

Tank Progress
• T1: 100% complete
• T2: 100% complete
• T3: 100% complete
• T4: 36% complete (currently in progress)
Next 7 Days (Planned Work)
Start T4 Interstitial works (around 15 Apr)
T4 Stage 3 (around 16 Apr)

This week marks the commencement of the Mobil Waipukurau project for TRL. Thanks to Fred for his earlier update covering...
23/03/2026

This week marks the commencement of the Mobil Waipukurau project for TRL. Thanks to Fred for his earlier update covering site-related items.

TRL’s weekly update, and photos of the completed tanks, T1 & T2.It is worth mentioning here that you may notice in the p...
06/03/2026

TRL’s weekly update, and photos of the completed tanks, T1 & T2.

It is worth mentioning here that you may notice in the photos that several sections in each tank appear more translucent than typical. For these layers the teams used powder-bound chopped strand mat instead of emulsion-bound (same GSM weighting). The resin has clearly wet through the glass fibres more effectively during lamination. As part of our ongoing process improvements, TRL will further investigate whether this offers any practical benefits for future tank builds. Any significant process or material changes would of course be developed in consultation with the client.

TRL ON SCHEDULE TRL’s tank builds remain on programme and are tracking well. We have also redesignated Monday 9 as a Fue...
28/02/2026

TRL ON SCHEDULE
TRL’s tank builds remain on programme and are tracking well.

We have also redesignated Monday 9 as a Fuel Installations changeover day, as only three days were previously allocated. Cleaning of the next tank is now scheduled for Tuesday 10, or as soon as changeover is completed.

Works completed this week –
* Stage 1 completed on T1 & T3
* Stage 2 interstitial layers completed to T1 & T3
* Stage 3 installed to T1 & T3

Upcoming Activities –
* Final resin coats (including wax)
* Striker plate installation
* Interstitial monitoring system install
* Final QA checks
* Tank scanning and testing

No safety incidents to report this week.