We are currently wrapping up a full refurbishment at a school in the New Forest, where we've been working across May half term and the summer holidays to avoid any disruption to term time.
The scope covered:
- Demolition and strip-out to form new layouts
- New stud walls, doors, and a sliding partition
- Two rebuilt toilet blocks
- A new breakout room
- M&E and ventilation
- Flooring throughout, and an external accessible walkway
Alongside this, we carried out the enabling works for the relocation of a cookery facility, coordinating access and service routes with the third-party contractor delivering the kitchen fit-out. Getting that sequencing right, so two separate teams could work the same space without getting in each other's way, was as much a part of the job as the trades themselves.
Final testing, snagging, and handover are now being completed ahead of the September return.