From challenge to solution, this is the Loomar Boerdery project.
Large irrigation pumps, high Eskom peak-time costs, flood-risk considerations, dust, and a demanding farming environment all had to be factored into one practical energy solution.
Class A Solar used real energy data to design a large-scale solar and battery system with 608 panels, raised steel structures, a waterproof and dustproof container, and an Eskom-approved feed-in solution.
The result: more reliable power for essential farm operations, electricity cost savings of more than 50%, and an improved expected ROI from 5 years to 3 years.
A solar solution built around the way the farm works.