Excited to be delivering Stage 1 works at the new Supashock facility in Holden Hill.Works currently underway include:• O...
20/05/2026

Excited to be delivering Stage 1 works at the new Supashock facility in Holden Hill.

Works currently underway include:
• Over 9,000sq/m of pavement preparation
• 142 bored piers
• Over 2,500m³ of cut to fill works
• Matching seamlessly into an existing operating business

Great progress so far and looking forward to pushing ahead with the next stages.

PavementPreparation BulkEarthworks

Excited to be delivering Stage 1 works at the new Supashock facility in Holden Hill.Works currently underway include:• O...
20/05/2026

Excited to be delivering Stage 1 works at the new Supashock facility in Holden Hill.

Works currently underway include:
• Over 9,000sq/m of pavement preparation
• 142 bored piers
• Over 2,500m³ of cut to fill works
• Matching seamlessly into an existing operating business

Great progress so far and looking forward to pushing ahead with the next stages.

AdelaideConstruction

Final stages at Mawson Lakes
27/04/2026

Final stages at Mawson Lakes

PROJECT UPDATE – 145 GRANGE RD, BEVERLEYNew home of Finsbury Green taking shape.• 10,000m³ Level 1 fill — sieved, recond...
23/02/2026

PROJECT UPDATE – 145 GRANGE RD, BEVERLEY

New home of Finsbury Green taking shape.

• 10,000m³ Level 1 fill — sieved, reconditioned & placed
• 6,000m² base prep underway

Great progress from the crew on site.

19/12/2025

Roll out. Merry Christmas ✌🏼

Big news Michael and I have teamed up to start a brand-new company — C2 Civil Crampton Contracting will still be running...
20/10/2025

Big news Michael and I have teamed up to start a brand-new company — C2 Civil

Crampton Contracting will still be running in the background with Michael as joint director, but from now on C2 Civil will be our new operating business.
We’re excited to kick off this next chapter together and keep building strong projects across SA.

Stage 1 complete in Tonsley Innovation District for
19/01/2025

Stage 1 complete in Tonsley Innovation District for

New project underway for
13/05/2024

New project underway for

Ballast and screenings placement ready for permeable pavers to be laid 🍐🍐🍐🍐——————Contact 0430 295 335admin@cramptoncontr...
31/01/2024

Ballast and screenings placement ready for permeable pavers to be laid 🍐🍐🍐🍐
——————
Contact
0430 295 335
[email protected]

Pm1 install for a new access road and tennis court @ Mercedes College. ——————Contact 0430 295 335admin@cramptoncontracti...
31/01/2024

Pm1 install for a new access road and tennis court @ Mercedes College.
——————
Contact
0430 295 335
[email protected]

Address

Adelaide, SA

Alerts

Be the first to know and let us send you an email when C2 Civil posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to C2 Civil:

Share