19/05/2026
Earthworks recently completed at Colac West Primary school.
Site cut and Sub grade rectification consisted of almost 2000m3 fill removed.
Just shy of 4000ton imported to replace subgrade with NDCR and cap with a class 2 subbase.
Great job to tick off the list, well and truly kept the wheels turning and booms swinging to get us over the line