03/06/2026
Huge effort from the blokes back in Tarawa, Kiribati. Started the west wing of the new Betio Hospital🇰🇮
All up 9 pour days.
10 slabs.
230 m³.
1300 m².
30°C+ temperatures.
Thank you to Reeves for looking after us and all the Local Kiribati workers for their hard work. See you all soon to finish it off💪😤