27/08/2026
Update:
Our team has spent the last 12 months providing material crushing & screening services to the newest and largest modern windmill turbine farm currently under construction.
The Uungala Wind Farm in Wellington NSW is now in the final stages of construction and completion will see it operating close to 70 functional turbines making it the largest of its kind in NSW and top 5 in Australia.
Our role in the project has been the crushing, screening & load out of approximately 800,000 combined tonnes of various materials for use on site including road-bases, drainage rock and backfill material.
Conditions have been challenging at times and a lot has been learnt along the way but the guys have met and exceeded all expectations to deliver.
We are extremely proud of our team for what they’ve been able to achieve so far on this project.