πŸ’§πŸ—οΈ π‚πŽπ‘π‘πˆπ†π„Μ 𝐀𝐄𝐏 β€” πƒπˆπŒπ„ππ’πˆπŽπππ„πŒπ„ππ“ 𝐃’𝐔𝐍 𝐑𝐄́𝐒𝐄𝐀𝐔 πƒβ€™π€πƒπƒπ”π‚π“πˆπŽπ 𝐃’𝐄𝐀𝐔 ππŽπ“π€ππ‹π„ πŸ“πŸŒβ”β”β”β”β”β”β”β”β”β”β”β”β”β”β”β”β”β”β”πŸ“Š πŸοΈβƒ£ πƒπŽπππ„Μπ„π’ 𝐃𝐔 ππ‘πŽπ‰π„π“πŸ‘₯...
08/05/2026

πŸ’§πŸ—οΈ π‚πŽπ‘π‘πˆπ†π„Μ 𝐀𝐄𝐏 β€” πƒπˆπŒπ„ππ’πˆπŽπππ„πŒπ„ππ“ 𝐃’𝐔𝐍 𝐑𝐄́𝐒𝐄𝐀𝐔 πƒβ€™π€πƒπƒπ”π‚π“πˆπŽπ 𝐃’𝐄𝐀𝐔 ππŽπ“π€ππ‹π„ πŸ“πŸŒ
━━━━━━━━━━━━━━━━━━━
πŸ“Š πŸοΈβƒ£ πƒπŽπππ„Μπ„π’ 𝐃𝐔 ππ‘πŽπ‰π„π“

πŸ‘₯ Population actuelle = 4500 habitants
πŸ“ˆ Taux d’accroissement = 2,5 %/an
πŸ“… Horizon = 20 ans
πŸ’§ Dotation = 60 L/hab/j
🌦️ Ks = 1,2
πŸ“† Kj = 1,15
βš™οΈ Kp = 1,8
⏱️ Fonctionnement = 18 h/jour
━━━━━━━━━━━━━━━━━━━
πŸ‘₯ πŸοΈβƒ£ ππŽππ”π‹π€π“πˆπŽπ 𝐅𝐔𝐓𝐔𝐑𝐄

πŸ“Œ Formule : P = P0 (1 + t)^n
➑️ P = 4500 Γ— (1,025)^20
➑️ P β‰ˆ 7371 habitants
━━━━━━━━━━━━━━━━━━━
πŸ’§ πŸ‘οΈβƒ£ ππ„π’πŽπˆπ π‰πŽπ”π‘ππ€π‹πˆπ„π‘

πŸ“Œ Qj = P Γ— dotation
➑️ Qj = 7371 Γ— 60
➑️ Qj = 442 260 L/j
➑️ Qj = 442,26 m³/j
━━━━━━━━━━━━━━━━━━━
🌦️ πŸ’οΈβƒ£ π‚πŽπ„π…π…πˆπ‚πˆπ„ππ“ π’π€πˆπ’πŽπππˆπ„π‘
πŸ“Œ Qs = Ks Γ— Qj
➑️ Qs = 1,2 Γ— 442,26
➑️ Qs = 530,71 m³/j
━━━━━━━━━━━━━━━━━━━
πŸ“† πŸ“οΈβƒ£ π‚πŽπ„π…π…πˆπ‚πˆπ„ππ“ π‰πŽπ”π‘ππ€π‹πˆπ„π‘
πŸ“Œ Qmax = Kj Γ— Qs
➑️ Qmax = 1,15 Γ— 530,71
➑️ Qmax = 610,32 m³/j
━━━━━━━━━━━━━━━━━━━
⏱️ πŸ”οΈβƒ£ πƒπ„Μππˆπ“ πŒπŽπ˜π„π
➑️ Qm β‰ˆ 9,42 L/s
━━━━━━━━━━━━━━━━━━━
βš™οΈ πŸ•οΈβƒ£ πƒπ„Μππˆπ“ 𝐃𝐄 ππŽπˆππ“π„
➑️ Qp = Kp Γ— Qm
➑️ Qp = 1,8 Γ— 9,42
➑️ Qp = 16,96 L/s
━━━━━━━━━━━━━━━━━━━
πŸ“ πŸ–οΈβƒ£ πƒπˆπ€πŒπ„Μ€π“π‘π„ 𝐃𝐄 𝐋𝐀 π‚πŽππƒπ”πˆπ“π„
➑️ Vitesse adoptée = 1 m/s
➑️ DN calculΓ© β‰ˆ 147 mm
➑️ DN retenu = 150 mm
━━━━━━━━━━━━━━━━━━━
πŸ“‰ πŸ—οΈβƒ£ π•π„Μπ‘πˆπ…πˆπ‚π€π“πˆπŽπ π‡π˜πƒπ‘π€π”π‹πˆππ”π„
βœ”οΈ Hauteur gΓ©omΓ©trique = 35 m
βœ”οΈ Pertes de charge
βœ”οΈ Pression disponible
━━━━━━━━━━━━━━━━━━━
πŸ’‘ π‚πŽππ‚π‹π”π’πˆπŽπ
βœ”οΈ Ks = variation saisonniΓ¨re
βœ”οΈ Kj = pointe journaliΓ¨re
βœ”οΈ Kp = pointe de consommation
πŸ‘‰ Ces coefficients garantissent un rΓ©seau fiable et bien dimensionnΓ©
━━━━━━━━━━━━━━━━━━━
πŸ‘·β€β™‚οΈπŸ’§ π‘π„ππŽπ†π„π— β€” π‡π˜πƒπ‘π€π”π‹πˆππ”π„ | 𝐀𝐄𝐏 | πˆππ†π„Μππˆπ„π‘πˆπ„

09/03/2026
26/01/2026
26/01/2026
26/03/2025

Burundi Engineering Business toujours lΓ  pour vous servir

Address

Bujumbura
69687385

Alerts

Be the first to know and let us send you an email when Burundi Engineering business posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share