First, the businesses down on Pleasant Valley BLVD North are still striving to keep their doors open and need your support now more than ever! Here is how to access them through the next phase of construction.
The City of Armstrong just released their updated timeline and on their website, shared what the next few weeks look like. Phase one is wrapping up and phase two starts shortly, her is how you can access our businesses.
Dates are approximate and subject to change:
▪️ Now (July 10): West side closed. Park in the three lots (Wood Ave, Pleasant Valley Blvd, old City Hall site) or on-street by Shepherd's, Okanagan St, Pleasant Valley Rd, and Patterson Ave.
▪️ Week of July 13: West side finishing up. Shepherd's Lane reverses to reach the west businesses, temporary parking opens on the south side.
▪️ Week of July 20: Full length opens, one lane south side. Shepherd's Lane closes, parking shifts to the west side.
▪️ July 27 on: Shepherd's Lane reopens, east side by Shepherd's closes for a while as they finish up.
For more details and contact information, please visit the City of Armstrong's website.