08/28/2025
On August 27, 2025 @ 6:45pm, under a beautiful blue sky the Heede crane was parked and tied down for the last time. Bob McSorley had the honor to complete the final run. Bob has been with Millar for over 47 years and has operated the Heede since it’s commissioning in 1981. A truly legendary accomplishment for Bob and an equally impressive story to add to the Millar Western history books! Bob's dedication and service to the company stands as an impressive part of both his legacy and the history of Millar Western.
The new crane has completed the initial commissioning phases and has successfully completed load testing. Trial runs with the new crane will begin mid-September following the laydown of the Heede.