27/09/2022
Project Update π§π Since our last update for this project, progress has been made with all but two of the plots receiving roof finishes, and we are starting to see windows brought to site and installed to make the plots weathertight. Mechanical and Electrical first fix has begun in most plots, and once all plots are weathertight, we will then see various finishing trades undertaking works such painting and decorating, fitting internal doors, skirtings and architraves, laying floor finishes, sanitaryware fit out, kitchen fit out and 2nd fix mechanical and electrical. Section 278 works will start early October, and the hard and soft landscaping on site will follow.
Project Team:
Liberty QS Ltd. - Contract Administrator / QS
GPS Projects Limited - Contractor
On Architecture - Architect
Considine - Structural and Civil Engineering
Henwood Green Ltd. - Client