26/02/2025
The image depicts a 110mm diameter pipe penetrating through a concrete floor slab. As part of our comprehensive fire containment strategy, our installation team implements a multi-layered fire stopping system consisting of:
1. Double layer of fire-resistant batts to provide initial thermal insulation and structural integrity
2. Intumescent fire collar that expands under heat to seal the pe*******on completely
3. Fire-rated compound application on the upper surface
This engineered solution creates an effective smoke and fire barrier, maintaining the floor’s designated fire rating and ensuring compliance with building safety regulations. The system prevents flame spread and toxic smoke transmission between floors in the event of a fire emergency.