14/10/2026
Episode 9 | The Fabric Was Selected. But Is It Still Right When It Arrives?
Series: PMC – The Things We Don't Talk About Date:
A fabric is selected today. But it may reach the machine two to three months later.
What happens in between?
PMC selection is normally based on the machine conditions and production requirements known at the time of placing the order.
But the fabric has a journey ahead:
Selection → Order → Manufacturing → Lead Time → Delivery → Storage → Installation
And several months may pass before it is finally mounted.
During this period, the machine or production requirements may change.
Perhaps the machine speed has increased. The basis weight has changed. A different furnish is being used. Vacuum conditions have been modified. Forming elements or operating practices have changed. Or the mill's production target is now different.
The fabric, however, was manufactured according to the original specification.
When it finally reaches the machine, we may be comparing its performance against conditions that no longer exist.
There is also the question of storage.
How long was the fabric stored? Under what conditions? Was it protected and handled appropriately?
These details can matter, depending on the fabric construction and materials.
So, when a newly installed fabric does not perform as expected, the question should not immediately be:
“Was the fabric selection wrong?”
It may be worth asking:
“What has changed between the day we ordered the fabric and the day we installed it?”
A useful practice could be to review the original selection parameters before mounting a new fabric—particularly when there has been a significant gap between order and installation.
Because the right fabric for the machine at the time of ordering may not automatically be the right fabric for the machine months later.
The selection may have been correct.
But the application may have moved on.
Small details. Big consequences.
💬 Do you review the original operating conditions before installing a fabric that was ordered several months earlier?
I'd be interested to hear how this is handled in different mills.