🔥 𝗔 𝗯𝘂𝗿𝗻𝗲𝗱 𝘄𝗶𝗻𝗱 𝘁𝘂𝗿𝗯𝗶𝗻𝗲. 𝗡𝗼 𝗿𝗲𝗺𝗮𝗶𝗻𝗶𝗻𝗴 𝗮𝗻𝗰𝗵𝗼𝗿 𝗽𝗼𝗶𝗻𝘁𝘀. 𝗨𝗻𝘀𝘁𝗮𝗯𝗹𝗲 𝘀𝘁𝗿𝘂𝗰𝘁𝘂𝗿𝗲𝘀 𝗶𝗻𝘀𝗶𝗱𝗲 𝘁𝗵𝗲 𝗻𝗮𝗰𝗲𝗹𝗹𝗲.
Recently, we completed the dismantling of a heavily fire-damaged wind turbine.
Before dismantling could be considered, the turbine had to be secured, unstable components stabilized, and safe access re-established. With critical lifting points destroyed by the fire, every step required detailed engineering assessment and careful planning.
One of the most challenging phases was repositioning the nacelle, rotor, and blade pitch to prepare the turbine for dismantling. 𝗗𝗲𝘁𝗮𝗶𝗹𝗲𝗱 𝗲𝗻𝗴𝗶𝗻𝗲𝗲𝗿𝗶𝗻𝗴 𝘀𝘁𝘂𝗱𝗶𝗲𝘀, 𝗿𝗶𝘀𝗸 𝗮𝘀𝘀𝗲𝘀𝘀𝗺𝗲𝗻𝘁𝘀, 𝗮𝗻𝗱 𝗰𝗹𝗼𝘀𝗲 𝗰𝗼𝗼𝗿𝗱𝗶𝗻𝗮𝘁𝗶𝗼𝗻 𝗯𝗲𝘁𝘄𝗲𝗲𝗻 𝗮𝗹𝗹 𝘁𝗲𝗮𝗺𝘀 𝘄𝗲𝗿𝗲 𝗲𝘀𝘀𝗲𝗻𝘁𝗶𝗮𝗹 𝘁𝗼 𝗺𝗮𝗸𝗲 𝘁𝗵𝗶𝘀 𝗽𝗼𝘀𝘀𝗶𝗯𝗹𝗲. ⚙️
A big thank you to our customer, to crane company Dartus Levage, our engineering team, and all colleagues on site. The successful completion of this project reflects the experience, flexibility, and problem-solving mindset that complex recovery operations demand.