Project DetailsProject Name:Mugu Karnali Storage Hydroelectric Project (1902 MW)Work Location:PilichaurTunnel Type:Test ...
27/05/2026

Project Details
Project Name:Mugu Karnali Storage Hydroelectric Project (1902 MW)
Work Location:Pilichaur
Tunnel Type:Test Adit Tunnel
Tunnel Size:2.5M Γ— 2.5M
Sub Contractor:-Dreamland Construction Pvt. Ltd.
Work Description:
Construction and excavation works for Test Adit Tunnel including drilling, blasting, mucking, ventilation, support works, and related tunnel activities.

06/05/2026
🚧 Project Update | Super Seti Hydropower Project (24 MW) πŸš§πŸ“ Location: Machhapuchchhre Gaupalika–1, KaskiπŸ“¦ Package: Acces...
02/05/2026

🚧 Project Update | Super Seti Hydropower Project (24 MW) 🚧

πŸ“ Location: Machhapuchchhre Gaupalika–1, Kaski
πŸ“¦ Package: Access Road Tunnel (Package-3)

We are proud to share the ongoing progress of our tunnel construction work under this prestigious hydropower project.

πŸ— Project Details:
β€’ Developer: B.N Energy Pvt. Ltd.
β€’ Contractor: Dreamland Construction Pvt. Ltd.
β€’ Design Consultant: TAC Consultancy Pvt. Ltd.
β€’ Tunnel Size: 5.00 m Γ— 4.75 m

βš™ Scope of Work:
βœ” Tunnel Excavation (Drilling & Blasting)
βœ” Rock Bolting & Ground Support
βœ” Shotcrete (Crete) Works
βœ” Survey & Alignment Control
βœ” Equipment & Manpower Management

πŸ“Š Current Progress:
βœ… 56% Work Successfully Completed

Our team is committed to delivering quality work with safety and efficiency, ensuring timely completion of this critical infrastructure.

πŸ™ We thank our dedicated team, partners, and stakeholders for their continuous support.

🚧 Project Completion Update | Upper Karnali Hydroelectric Project (306 MW) πŸš§πŸ“ Location: Mugu District, NepalπŸ“‘ Contract N...
29/04/2026

🚧 Project Completion Update | Upper Karnali Hydroelectric Project (306 MW) 🚧

πŸ“ Location: Mugu District, Nepal
πŸ“‘ Contract No.: EE-DL-TA-2025/001

πŸ— Work: Test Adit Tunnel Excavation
πŸ‘· Contractor: Dreamland Construction Pvt. Ltd.
🀝 Client: Elevate Energy Pvt. Ltd.

βœ… Project Successfully Completed (100%) – On Time

We are proud to announce the successful and timely completion of the Test Adit Tunnel Work under challenging site conditions.

πŸ“Š Completed Works:

β€’ Tunnel Excavation: 375 meters
β€’ Cavern Excavation: 6m Γ— 6m Γ— 5m

βš™ Major Activities Executed:

βœ” Portal clearing & access preparation
βœ” Army coordination & site management
βœ” Explosive supply, storage & blasting operations
βœ” Drilling, blasting & tunnel excavation
βœ” Mucking, loading & disposal
βœ” Geological mapping & geotechnical investigation
βœ” Rock support & scaling works
βœ” Convergence monitoring system installation
βœ” Survey control, alignment & level works
βœ” Ventilation & dewatering systems
βœ” Temporary power & lighting setup
βœ” Equipment mobilization, maintenance & repair
βœ” Daily progress reporting & documentation
βœ” Safety management & risk control
βœ” Manpower camp setup & logistics

πŸ‘ This achievement reflects strong teamwork, technical excellence, and dedication in delivering quality work safely and efficiently.

πŸ™ Special thanks to our team, client, and all stakeholders for their continuous support.

Project StatementThe Rauje Khola Hydropower Project (18.6 MW) is currently under construction at Solududhkunda Municipal...
23/04/2026

Project Statement
The Rauje Khola Hydropower Project (18.6 MW) is currently under construction at Solududhkunda Municipality–01, Solukhumbu, Nepal. The project is being developed by Hydro Connection Pvt. Ltd., with design and supervision by CEPAD Hydro Consultant Pvt. Ltd., and the construction works are being executed by Dreamland Construction Pvt. Ltd.
The project includes a tunnel of size 3.20 m Γ— 3.20 m with a total planned length of 1000 meters. As per the latest progress update, 434 meters of tunnel excavation has been successfully completed.
This represents an overall physical progress of 43.40%, indicating that the project is progressing steadily. The project is currently ongoing, with the remaining works focused on completing the balance tunnel excavation and associated construction activities.
We would like to express our sincere appreciation for the opportunity to be part of this project and remain committed to delivering the work with quality, safety, and within the stipulated timeline.

12/02/2026

SSHP- 24MW
Tunnel Access Road

RKHP-18MW
10/02/2026

RKHP-18MW

Address

Bhaktapur
01

Telephone

+9779865611342

Website

Alerts

Be the first to know and let us send you an email when DREAMLAND CONSTRUCTION PVT.LTD posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to DREAMLAND CONSTRUCTION PVT.LTD:

Share