11/12/2019
How a building is divided into 100% of all of the items together. Sample its potential.
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME (Lift, Generator, Substation) = 10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
1.STRUCTURE 35% (That way)
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100%
2.BRICK WORK 6% (That way)
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100%
3.WOOD WORK 5% (That way)
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100%
4.METAL WORK 2% (That way)
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100%
5.PLAMBING & SANITARY 6% (That way)
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100%
6.ELECTRICAL - 7% (That way)
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100%
7.PLASTER 4% (That way)
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100%
8.GENERAL FLOOR TILES 6% (That way)
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100%
9,TOILET & KIT WALL TILES = 3% (That way)
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100%
10.ALUMINIUM WORK 4% (That way)
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100%
11.EME (Lift, Generator, Substation) 10% (That way)
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100%
12.PAINT WORK = 3% (That way)
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100%
13.OTHERS CIVIL WORK = 6% (That way)
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100%
14.UTILITY CONNECTION & BILL = 3% (That way)
- Desa/Desco = 35%
- Titas = 20
- Wasa = 15%
- Utility bills = 30%
TOTAL = 100%