๐ง Pirongia Bridge Demolition ๐ง
Following severe flood damage in February 2026, the Pirongia Bridge required urgent removal to restore safety and access for the community.
Once the Bailey bridge was installed, Nikau mobilised immediately, deploying 50T and 20T excavators to take on the challenge.
Ex*****on highlights:
โข Bridge fully removed from a ~4m deep river in just 1 day
โข Total project completed in 3 days
โข Delivered safely and efficiently under tight timeframes
Working alongside Fulton Hogan and Waka Kotahi, Nikau was selected for our high-capability machinery and ability to mobilise fast when it matters most.
This project is a great example of what can be achieved with the right team, the right gear, and a clear plan.
Proud of the crew for another fast, safe, and high-quality delivery.