Silkwood Estate Cairns

Silkwood Estate Cairns Silkwood Estate Cairns

Lot 66A/C’s are complete, landscaping & fencing done, carpet done, first clean finished, silicone/letterbox/clothesline ...
02/04/2015

Lot 66
A/C’s are complete, landscaping & fencing done, carpet done, first clean finished, silicone/letterbox/clothesline installed and my final inspection done. Next week I will have the touch ups done and final clean done ready for rental.

Lot 64Render is finished, ceiling battens are up and the frame/eave delivery is going to site today along with a site cl...
02/04/2015

Lot 64
Render is finished, ceiling battens are up and the frame/eave delivery is going to site today along with a site clean too. Next week I will have the walls up, eaves done, external doors hung, external paint done and windows installed.

Lot 56Landscaping and fencing is done so everything is finished ready to go for rental
02/04/2015

Lot 56
Landscaping and fencing is done so everything is finished ready to go for rental

Lot 53Fascia/gutter/battens complete and renderer started today and will finish on Sat. Next week I will have the roof f...
02/04/2015

Lot 53
Fascia/gutter/battens complete and renderer started today and will finish on Sat. Next week I will have the roof finished, ceiling battens installed and deliveries for wall frame delivered ready to stand walls the following week.

Lot 66Painting was completed, plumbing fit off is done, fencing started and the electrical fit off which will be finishe...
20/03/2015

Lot 66
Painting was completed, plumbing fit off is done, fencing started and the electrical fit off which will be finished Monday. Next week I have the A/C’s fitted off externally, garage door installed, insulation booked, shelving, shower screens/mirrors/robes go in, landscaping and carpet get done.

Lot 64Blocks were done, rough ins completed, bondbeam poured and trusses were stood today. Next week we will aim to get ...
20/03/2015

Lot 64
Blocks were done, rough ins completed, bondbeam poured and trusses were stood today. Next week we will aim to get the roof on if the rain stays away.

Lot 56Fit offs are complete, locks done, insulation in, screens/mirrors/robes installed, shelving don , first clean fini...
20/03/2015

Lot 56
Fit offs are complete, locks done, insulation in, screens/mirrors/robes installed, shelving don , first clean finished and driveway set up. Next week we will pour driveway, finish carpet, start fencing, landscaping, silicone, blinds and final clean … ready for handover with you on Friday.

Lot 53Well we got the stormwater done and blocks delivered then the blocklayer kicked of … but management made the call ...
20/03/2015

Lot 53
Well we got the stormwater done and blocks delivered then the blocklayer kicked of … but management made the call to not go any further until we knew what we were looking at with the cyclone encroaching as we didn’t want to lay blocks then have to clean up and start again, so Monday we will kick off again now Nathan has blown past and pour bondbeam Thurs to stand trusses Fri.

Lot 66Stair walls were plastered and painter has kicked off, next week the painter will finish and I will get deliveries...
16/03/2015

Lot 66
Stair walls were plastered and painter has kicked off, next week the painter will finish and I will get deliveries on site with a view to start fit off Fri. Should get the fence posts in and hopefully prep the yard for landscaping.

Lot 64Blocks were delivered and the blocklayer got as far as setting out and loading blocks and hasn’t been able to star...
16/03/2015

Lot 64
Blocks were delivered and the blocklayer got as far as setting out and loading blocks and hasn’t been able to start laying as yet. Next week I have the bondbeam pour booked for Wed and stand trusses on Thurs.

Lot 56Fit offs 95% complete, weather should let us finish external fit off Monday. Next week I have insulation, shower s...
16/03/2015

Lot 56
Fit offs 95% complete, weather should let us finish external fit off Monday. Next week I have insulation, shower screens/robes/mirrors, garage door, shelving and first clean booked. Driveway also if the ground will accept the machine to dig and trim.

Lot 53Slab was poured and that is as far as we have got due to weather, blocklayer will start as soon as he finishes 64 ...
16/03/2015

Lot 53
Slab was poured and that is as far as we have got due to weather, blocklayer will start as soon as he finishes 64 which should be Wed subject to rain.