Day 08 Construction journey 🏗️. Assalam-o-Alaikum! Today is Day 8 of our construction journey. Alhamdulillah, the foundation brickwork has been completed. The first DPC has been laid in the foundation. After that, for additional protection, we used chemical treatment and a membrane sheet to complete the second DPC as well. The purpose is to protect the foundation from moisture and dampness, preventing any moisture from rising upwards in the future and keeping the house strong and protected. Alhamdulillah, today’s work has also been completed successfully. InshaAllah, we’ll share the next stage of the construction journey with you. MOJ ESTATES
SAJAWAL ISMAIL
03008488786
34 CCA Phase 6 Dha Lahore.

15/09/2026

(Day -08) Construction journey. Assalamu Alaikum, today another important stage of our construction journey has started. The brickwork for our foundation has officially begun. The foundation walls are being constructed according to the approved drawings and measurements. Two 27-size rebars, two 22-size rebars, two 18-size rebars, and two 13-size rebars have been installed underneath the foundation. All the work is being carried out according to the engineering drawings and design to ensure a strong, durable, and high-quality foundation for our home. InshaAllah, this strong foundation will be the beginning of the next stage of our house construction. One brick at a time alone step at a time dream structure is slowly becoming a reality. ESTATE MOJ. SAJAWAL ISMAIL. 03008488786 Info By Sajawal ®️

13/09/2026

( DAY 07 ) Dha 9 Town Construction journey. 🏗️. concrete work started & Base bed laid. Assalamualaikum! Today is Day 6 of our Construction Journey. Today, we completed an important stage of our foundation work. We mixed the aggregate, sand, gravel, and cement properly and laid a 4-inch layer to make our foundation stronger and more durable. After that, we used a compactor machine to properly compact the bed and make it firm and well-prepared for the next stage of construction. Alhamdulillah, our Construction Journey is moving forward step by step. MOJ ESTATES. SAJAWAL ISMAIL 03008488786. 34 CCA Dha Phase 6.

13/09/2026

Day 05
Construction journay day 05 Termite spray work this is best work for foundations contact : 03008488786

12/09/2026

Apex House for sale in Dha 9 Town contact : 03008488786

11/09/2026

Dha 9 Town construction journey
Day 04 - EXCAVATION
Day1 - Cleaning & leveling
Day2 - Marking
Day3 - Excavation begins
Day4 - Excavation day2 or bore work

Today, we moved forward with the next important steps of our construction journey. The bore work was completed ,
Step by step the plot in transforming into a proper construction site - and every day bring us closer to the final project. 🏗️
MOJ ESTATE
SAJAWAL ISMAIL
03008488786
34 CCA1 DHA PHASE 6, Lahore

10/09/2026

Dha 9 Town construction journey.
Day 03 Excavation - Day 1 🏗️
Day 1 - cleaning & laveling
Day 2 - Marking
Day 3 - Excavation begins

Today was day 1 of the excavation work, and the continued steadily through out the day. The excavation in progressing step-by-step as we prepare the plot for the foundation and the next phase of construction.

Every day bring us one step closer to turning this simple plot into a complete project 🏗️

Moj Estate
SAJAWAL ISMAIL
03008488786
34 CCA Dha phase 6 ,Lahore

09/09/2026

Day 02
Construction update
Day 2 of our construction journey is officially complete !
Today we complete the plot marking - the first important step toward turning a plan into realty.
Every detail matters .every measurement counts.

MOJ ESTATES
SAJAWAL ISMAIL
03008488786
34 CCA Dha Phase 6

08/09/2026

Dha 9 Town Construction journey Begins (Day-1)🚩 Info By Sajawal ®️ From an overgrown plot to the beginning of a new construction journey ! Our Dha 9 Town project officially begins with proper site cleaning , leveling and preparation with great cooperation from Dha,the site is now ready for the next big step- Foundation work • This is just the beginning ... Follow us as we turn this empty plot into a complete construction project .

SAJAWAL ISMAIL
03008488786. Moj Estate Dha phase 6 cc1 Lahore. Real Estate | investment | construction

Address

34CAA1 , Phase 6/Second Floor
Lahore
54000

Website

Alerts

Be the first to know and let us send you an email when Realtor Info by Sajawal posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share