Old Meadows Ranchos Community & Water Company

Old Meadows Ranchos Community & Water Company An update page about what's going on in the Old Meadows Ranchos neighborhood.

Ta-DA, all major violations removed, finally.
11/16/2023

Ta-DA, all major violations removed, finally.

10/26/2023

A few small updates and a short outage this Friday (this is the same as the document distributed today)

Planned outage and work:

This Friday at 9am (10/27/23) the water will be shut off for an approximate 5 hour outage. There will be no water service during this time. This is so that we can give some attention to the tank manway as we currently have a small leak.

We plan on draining the tank so that we can re-seat the gasket (as well as measure it to order a new one if this is unsuccessful). Once this is complete, we will allow the silicone to set for a while before starting to refill the tank which will take a while to get to a level to start back up the system. The aim will be to get the system back online by midafternoon.

Tank Cleaning:

Thank you for all of the help from Dana, Lyle, Pete, Melinda and her children, Joey, Kylie, Daniel and his children, Jenny and Ari for helping to shovel out the water tank. We found once it was drained that we had a foot of silt in the base of the tank, as well as a 4-foot-high mountain of silt around the well inlet. This was more than we had hoped so thank you for the help and patience of the community. I would suggest in 10 years we come together on a Saturday and repeat this. With the Variable frequency drives that we have on the wells it should reduce the amount of silt into the tank, but it will not cease all of it.
Wellhouse infrastructure and progress: (Plus explanation of why we will have a day/few days of intermittent pressure during the days)
The work done on the same day as the tank cleaning went successfully. The new well and booster pump system has been tied in parallel, with the existing systems still attached with numerous valves. All hard piping is complete at this point and is ready for startup. The final meeting with USDA occurred yesterday with everything being approved (other than two “Made in India” metal covers that need to be swapped out due to American Steel directives within the USDA).

What are the next steps?

We are planning an approval meeting with the Regional Engineer to confirm that everything is now complete to the standard of the Division of Drinking water, this will mean that the operating permit is issued. Once that is done, hopefully early next week, we will be ready to test the new equipment.

When we test the booster pump system there will be a day with intermittent pressure. This is as we test the new system and get all the settings programmed properly. We will alert everyone of this day as soon as it is planned.

The new well we will start test pumping to get it to a point where we can limit the amount of silt that it may draw up from the well. It may need some weeks of development before we do the switch over to the new well. This should not affect the pressure of the system given the booster system is independent and runs directly from the tank.

Proposition 3:

Thank you for the responses that I got back for the mail-in proposition 3. We needed 9 votes to reach the quorum for the vote which is exactly what we received.
The votes were:

For: 8 Against: 1 Abstain: 0

From these votes the proposition has passed, and the bylaws are being updated with all of the approved propositions and will be available in due course. The Cross Connection Control document that was also approved will be also available in due course.

10/11/2023

Edit: The Rag has been removed from the tank and the tank has been filled. An update text will be sent around about 6am but it is below for those who are up at this hour who haven't just got back from the pumphouse property!

A temporary update: when cleaning the hatch on the tank our engineer managed to drop a rag into the tank. Given that we don’t want one of our pumps chewing it up we have left the tank to settle then will go searching for it in two hours. If that is successful we will be then filling the tank and once the tank pressure is high enough we will start the distribution pumps.

We are expecting the water to have silt as well as chlorine in it. We suggest not drinking it for a few days as we flush the chlorine out and the silt has a chance to settle.

A big thank you to Dana, Lyle, Pete, Melinda and her children, Joey, Kylie, Daniel and his children, David, Jenny and Ari for helping shovel out the tank, as well as on site help from our engineer Bert and the use of the contractors suction truck!

Well, we're at this point!
10/10/2023

Well, we're at this point!

We're still at it. The water won't be able to be turned back on until the tank is empty of silt. It's getting there, but...
10/10/2023

We're still at it. The water won't be able to be turned back on until the tank is empty of silt. It's getting there, but it was really really high in places.

Still going!
10/10/2023

Still going!

Here we go!
10/10/2023

Here we go!

09/30/2023

Meeting Saturday at 10am at the Library! Please attend, as we have a lot to vote on!

09/11/2023

Our meeting date has changed from September 23 @ 10am to September 30 @ 10am, still at the library. It has also changed from the East to the West room (we will have a sign on the door just to avoid confusion). Updated notices will be sent out via text, call, or email, or be delivered by hand around the neighborhood.

TA-DA! The piping from the new well to the new pumphouse is complete. The insulated house over the well is complete as w...
08/15/2023

TA-DA!
The piping from the new well to the new pumphouse is complete. The insulated house over the well is complete as well as the pumphouse building being up!

Next is the electrics within the Pumphouse, insulation for the pumphouse. Once those are complete which will take a bit of time all that will be left is connection to the system!

08/07/2023

Saturday night was our neighborhood ice cream social outside at the Hadlock's home. We had 24 people in all show up at various times. Everyone there seemed to really enjoy meeting some new neighbors, visiting., and having ice cream, cookies and drinks. Thanks to all who came and who brought things to share. It was a very nice evening and we hope to do it again in the future and hope many more of you will come!

07/31/2023

We have issued an apology for a previous misunderstanding of the ByLaws; we have changed our most recent addition to the ByLaws and instead added it to the Rules and Regulations.

Packets for our next meeting have been distributed to those neighbors that were home, and will be mailed to those who were unavailable or emailed to those who requested it be sent that way. No date officially planned yet but we hope it will be on a weekend in September everyone has free so they can attend.

Address

N 5300 W
Cedar City, UT
84721

Alerts

Be the first to know and let us send you an email when Old Meadows Ranchos Community & Water Company posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share