08/12/2026
We've been hard at work in Hillsboro! π¦ Crews have completed all underground utilities and poured the floor slab for the pool building, paving the way (literally) for masonry walls to begin. Forming of the leisure pool and lazy river floors are underway with pours planned for early next week, and excavation has begun for the slide foundations with installation beginning at the end of the month.