Full renovation from a blank slate to a luxurious bathroom. We commenced with an almost entirely gutted bathroom. We completed the framing for the tub. We then finalized all plumbing work prior to installing drywall and patching any holes created during demolition. The tub and surrounding tile were installed. The walls were finished and sanded before applying paint. LVP flooring was installed prior to bringing in the vanity, mirror, shelf and toilet.
Job well done!!