We finished up the duplex building pad project yesterday morning. This phase of the project involved excavating and leveling the building pad areas to the required elevations while efficiently managing the cut material from the site.
A large amount of material was loaded and hauled across the road to separate future building lots where it will be utilized as fill material for building pads in the future. Moving and reusing material in this manner helps keep future development moving efficiently while reducing the need for imported fill.
After excavation and hauling operations were completed, the duplex pad areas were graded in preparation for the builder to start construction. The future pad areas across the road were rough graded in preparation for future additional fill and site prep. Always good seeing a project start coming together from the ground up.