Let’s talk about why HERS inspections slow down projects 👇
Most delays I see aren’t caused by the city — they’re caused by:
• HERS raters being brought in too late
• Missing CF1R / CF2R / CF3R paperwork
• Changes in the field that don’t match the energy model
• Poor communication between trades
• Expecting “same-week” inspections during peak season
HERS compliance isn’t optional, and it isn’t instant.
If contractors treat it like a final checkbox instead of part of the planning phase, delays are guaranteed.
The solution?
📌 Early coordination
📌 Clean documentation
📌 Clear expectations