Changes in the Real Estate Development industry are constant and Prime Development Group is always at the forefront. Our expertise in new building technologies, space planning and project management, have created new standards in each area. Additionally, our in-house capabilities allow us to respond quickly to your needs and mobilize our forces on demand. "We tap into the vast experience of our te

am of experts to get you answers instantly." Our real estate advisors analyze relevant real estate information and use it to develop creative strategies and implement effective plans. The skilled professionals at Prime Development Group will lead you through the complicated world of real estate development with intelligence and vigilance. The intellectual capital of our professionals who live and work in the markets they serve, helps them form sound decisions. Building relationships, tracking trends and giving you the services you need to deliver superior business performance is the essence of our firm.

04/19/2023

All buildings have Certificates of Occupancy.

12/15/2022

We have CO for building A and have folks moving in. Building B will be following in January.

11/09/2022

Landscaping is done for C&D. Building A will be handed over to the management company next week. Building B has finished interior paint and has now started cabinets. Building E will be done with drywall at the end of December.

10/20/2022

Landscaping has started going in. Building D is starting to have a few residents move in. Building C is having touch ups done then will start having folks move in. Building A should be online in 3 weeks or so.

09/27/2022

Pavement is down. Building D is shooting to go online next week, with building C the week after. Then Building A end of Octoober. Building B Top of December and E in January.

08/22/2022
07/19/2022

Serenity
We have filled the pond in and are going to finish the site work and head into paving. PSE has energized the transformers on site. All the metal siding is complete on C & D. The hardie has started prime and paint. Prime and paint has also started on the inside of D.

06/09/2022
06/02/2022

Serenity main power conduit is going in on the week of the 13th then power gets hooked up the week of the 27th.

05/27/2022

Building A has started bottom floor siding and is ready for decks.
Building B has all the windows in and is ready to start decks.
Building C & D will be starting drywall next week and is 90% done with siding.
Building E is still being roughed in and dried out.

05/16/2022

Serenity
All roofs are done
Building A is all wrapped and is drying out
Building B is about 60% wrapped and is also drying out
Building C & D are dried out and will be getting insolated this week and next week
Building E is drying out and being roughed in for plumbing, electrical, and fire sprinkler

04/28/2022

Building A will be receiving it roof on 5/2
Building B will be done with rough in by the end of may
Building C & D will start drywall the second week of may
Building E has started the rough in

Address

7843 Old Highway 99 SE Hangar M-5
Tumwater, WA
98501

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

+13605282550

Website

Alerts

Be the first to know and let us send you an email when Prime Development Group LLC. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Prime Development Group LLC.:

Share