21/09/2015
Some of the work we did at Sebenza SAPS:
- The facility consisted of 9 blocks.
- 3 blocks were demolished in order to make way for the new parking.
- The remaining 6 blocks were refurbished to receive new paint to ceilings and walls, new floor finishes changing from vinyl tiles to ceramic.
- The facility received concrete palisade fence.
- Ordinary toilets were converted in order to accommodate paraplegic people.