Welcome back to our Silverbrooke, Ruwa residential construction project update!
In this video, we take you through the progress made since our last update. The project has now advanced from slab level to brickwork completion at window level, marking another significant milestone in the construction process.
✅ Foundation completed
✅ Ground beam and slab completed
✅ External and internal wall brickwork completed to window level
✅ Openings for doors and windows formed
🔜 Ring beam construction next
It's exciting to see the structure taking shape as the floor plan becomes more visible and the spaces begin to come to life. This stage is critical in ensuring accurate wall alignment, proper openings, and a strong base for the ring beam and roof structure.
We appreciate everyone following the journey and supporting our work. If you're planning to build in Zimbabwe and would like us to manage or construct for you from start to finish, feel free to get in touch.
📍 Project Location: Silverbrooke, Ruwa, Zimbabwe
"The walls are up, the vision is becoming reality, and next we'll be casting the ring beam. Stay tuned for the next update!"