The Downingtown train station is moving half a mile east.
The new station is going where the tracks cross US 322, Brandywine Avenue. The reason is the track itself. The current station sits on a curve, and that curve is what keeps it from having high platforms that meet ADA standards. The stretch at 322 is one of the few straight sections in the borough.
Here’s what’s planned there. 2 high-level platforms for level boarding, east of 322, with Amtrak and SEPTA both still stopping. A new railroad bridge over 322 to replace the stone arch the trains cross on now, with the clearance going from 12 feet to 16 feet. Parking lots in all 4 corners of the crossing, about 480 spaces, with an elevator and stair tower in each corner. And pedestrian bridges over 322 at platform level, so people don’t have to cross the road on foot.
Some of the work has already started. The old interlocking has been removed, and the foundations for the new overhead wire structures are poured. Utility crews have been moving pole lines along Boot Road, Reed Street and 322 since June, and that’s scheduled to wrap up in February 2027.
2 week long bores under the tracks are tentatively planned for December or January, with no work over the holidays. Amtrak crews are also working on the overhead wires at night, and that runs for several months.
The station itself starts construction in mid-2027, and PennDOT is projecting 2031 to finish.