U.S. Permitting Brief — September 28, 2026
Washington — residential land-use review rules changed, effective June 11. For covered project permits, completeness is procedural, and an application is deemed complete on day 29 if the local government has not given written notice that it is incomplete. State agencies and certain districts also face review deadlines and fee-refund requirements. Local decision deadlines are generally 65, 100, or 170 days, depending on notice and hearing requirements, but local rules can modify the categories and the law excludes some review periods. These rules cover land-use and environmental permits; they do not cover building permits issued under building codes.
Follow up: On Washington residential entitlement work, record the completeness date, confirm the jurisdiction’s permit category and local deadlines, and track referrals to utilities or other agencies.